Tag: Orange County Drainage District

2021 Little Cypress Bayou Waterway Debris Removal Project NRCS/USDA

The Orange County Drainage District has commenced its Bayous Debris Removal Project, which involves primarily the removal of fallen trees and other vegetative debris from within Adams Bayou, Cow Bayou and Little Cypress Bayou. The purpose of the Project is to remove this debris from these three bayous that so that drainage is not impaired within these bayous, each of which serve to drain significant portions of Orange County. The Cow Bayou Watershed originates in Jasper County, the Adams Bayou watershed originates in Newton County, and the Little Cypress Bayou watershed originates in Orange County. All three bayous drain into the Sabine River.

The District has secured grant funding from the Natural Resources Conservation Service, a division of the U.S. Department of Agriculture, to help pay for a large portion of this Project. The total cost of the Project is estimated to be approximately $1.5 million. The Drainage District has contracted with Aftermath Disaster Recovery, Inc., which provides multiple barge units equipped with grapple and saws, to assist with the Project.

The first component of the Project is the removal of the debris from Little Cypress Bayou.  The Project began on Thursday, June 3, 2021. The scope of the Little Cypress Bayou project (depicted in the map above) includes removal of debris within and along Little Cypress Bayou from the Sabine River to FM 3247.  The photos below document the progress of the project to date.  More photos will be added as they become available.

On 6/11/2021 Aftermath Disaster Recovery, Inc., and the Orange County Drainage District completed the debris removal project on Little Cypress Bayou, resulting in more then 4200 cubic yards of debris being removed from the Bayou.

Cole Creek Project Phase 2

The Cole Creek Project Phase 2 involves the regrading of Cole Creek (depicted in orange on the map above) from Interstate 10 north for more then 6 miles. In Cole Creek Project Phase 1, Cole Creek from Interstate 10 south to the rail road tracks just above Cow Bayou. Cole Creek drains into Cow Bayou causing the structure to be impacted by the conditions of the Bayou, including tidal influences. 

The Cole Creek Project Phase 2 also includes the evaluation (checking for positive drainage) of each tributary to Cole Creek, that drain the surrounding areas.

Currently operations are being performed on two tributary ditches to Cole Creek. One tributary Drains from Highway 1442 to Cole Creek and is adjacent to the North side of the Southeastern Freight Lines building located off of Highway 1442. The second tributary that the District will be making improvements to drains from Highway 1442 to Cole Creek and it located on the east side of Highway 1442 across from Bland Road. Upon completion of the two tributaries referenced above the District will resume operations on Cole Creek. (Updated 8/19/2021)

The Cole Creek Drainage Improvement Project (Phase II) was successfully completed in late 2022. Please see the photographs below additional details of the nature and scope of the work performed before, and after, completion of the Project.

Cole Creek Project (Phase II) Prior To Improvements

Cole Creek Project (Phase II) Completion

Terry Gully Project Phase 2

Terry Gully Project Phase 2

The Terry Gully Project Phase 2 involves the regrading of Terry Gully (depicted in orange on the map above) from Interstate 10 to North Tram Road. Previously the District completed the Terry Gully Phase 1 Project whereby it improved Terry Gully from Interstate 10 south to Terry Road. Terry Gully drains into Cow Bayou causing the gully to be impacted by the conditions of the Bayou, including tidal influences. 

The Terry Gully Project Phase 2 also includes the improvement by the regrading of many tributary ditches (depicted in green on the map above) to Terry Gully, that drain the surrounding areas.

Photos will be added to this post as the project progresses.

Adams Bayou/Tributaries

This is an update on the latest Orange County Drainage District maintenance of Adams Bayou and tributaries.The scope of this project is to regrade and improve a series of drainage structures in the north eastern portion of Orange County. The drainage structures include Adams Bayou (which flows from the north eastern part of Orange County to the Sabine River) as well as the many tributaries feeding Adams Bayou that assist in draining the surrounding areas. The green areas depicted on the map above indicate each ditch and drainage structure that will be involved in the improvement project.

Check back for additional updates and photos of the Orange County Drainage District maintenance of Adams Bayou and Tributaries Project.

Susan Circle North Outfall

Orange County Drainage District makes improvements to the Susan Circle North Outfall

Here is an update of our progress as the Orange County Drainage District makes improvements to the Susan Circle North Outfall. The North Susan Circle Outfall receives storm water from Spooner Street, Nelson Street, Tower Road, Joel Street, Louise Street and surrounding areas. The current scope of work for this project includes the excavation and grading of the Outfall, commencing work at Highway 1442, and then proceeding north and west until completion northwest of Spooner Street, as depicted by the pink line in the map shown above. Previously the District has excavated and graded the Susan Circle Outfall south of Highway 1442 to the location where it ties into the Bessie Heights Marsh. Due to the Outfall connecting to the Marsh, drainage within this Outfall is tidally influenced.

Check back for additional information and photographs as Orange County Drainage District makes improvements to the Susan Circle North Outfall ditch.

Office Administrative Assistant

The Orange County Drainage District is taking applications for employment for the position of Office Assistant. Refer to the .PDF below for additional information.

F-5 Lateral Outfall

The F-5 Lateral Outfall receives storm water from Lakewood Estates, Colonial Lane Estates and surrounding areas. The current scope of work for this project includes the excavation and grading of the F-5 Lateral Outfall, from Terry Gully to Orange Street, which is depicted by the pink line in the map shown above.

The District completed this project in the middle of May, 2021.

Oldbury Road and Farragut Heights Outfalls

The Oldbury Road Outfall receives storm water from Highway 105 and surrounding areas, and then merges with the Farragut Heights Outfall, which generally provides drainage for the area east of Highway 105 in the general area of Farragut Heights, Becky Circle, Oldbury, Pug Road and Corbett Street. The scope of work for this project includes the excavation and grading of the Oldbury Road and Farragut Heights Outfalls, which are depicted by the pink line in the map shown above.

SRA Toe Ditch

The SRA Toe Ditch runs parallel to the SRA Canal, originating immediately south of FM 1078 and west of FM 1130, and drains into Adams Bayou. The project consisted of deepening and widening the ditch to grade, beginning at a location near Adams Bayou and terminating at FM 1078. The project was completed in May of 2019.